E-SPLOST Projects
Projects Currently in Planning/Construction Phase
Multi-School (Holston, Burks, Clarke Central, H.T. Edward campus, Gaines) HVAC replacements - Expected completion Fall 2024
Coile Health Center Project - Expected completion October 2024
HTE-Classic City High School Health Center Project - Expected completion October 2024
Cedar Shoals HS - Renovation Project - Expected completion Fall 2025
Clarke MS - Expected completion - Phase 1 - Fall 2024 / Phase 2 - Early 2025
Aerial (2023)
Aerial (2024)
Timelapse Videos (2023)
Completed Projects
ELC East - Loaded Dock Repair Project - Completed April 2024
Mutli-School (BHH, CRE, FOW, GNS, HBS, HTE, JJH, JLB, TIM, WDV, WIN) Whiteboard Replacement Project - Completed July 2024
ACCA Bio-Manufacturing Lab (Also includes A/V Lab renovations) - Completed August 2024
Culinary Kitchen @ ACCAcademy - Completed Fall 2023
Clarke Central HS Roof/Masonry Project - Completed Fall 2023
ELC-EAST - Earth Shelter Roof Project - Completion Fall 2023
Cedar Shoals Field House - Completed June 2023
360 Photos (11-4-2022) - Weightroom Upper Patio View / Football Office View / Upper Level Main Entrance
Drone Videos (11-8-2022) - Field side flyby / Stadium & Fieldhouse
Drone Videos (2-1-2023) - Field side flyby / Stadium & Fieldhouse
Clarke Central Softball Dugout Expansion - Completed September 2022
Early Learning Center-East @ Old Gaines School - Completed May 2022
Kitchen Upgrade @ HT Edwards Early Learning Center - Completed April 2022
BOE Administrative Offices (595 Prince Ave) - Completed March 2022
Project Photos - The Vernon Payne Meeting Hall
Clarke Central Stadium Project - Completed Spring 2021
Aerial Views - Home Side - Visitor Side
Cedar Shoals Track Project - Completed Spring 2021
ACCA Industrial Lab - Completed October 2020
Cedar Shoals Locker Rooms and Old Gym Upgrades - Completed Summer 2020
Clarke Central Softball Concession Stand/Pressbox and Field upgrades - Completed September 2019
Photos - 360 Photo
Hilsman Middle School - Completed September 2019
2018 Aerial Photos - December - November - October - August - July
2019 Photos - February - January
Burney-Harris-Lyons Middle School - Completed March 2019
Coile Middle School - Completed March 2019
ACCA Cosmetology Lab - Completed December 2018
Oglethorpe Avenue Elementary - Completed Fall 2018