E-SPLOST Projects

Projects Currently in Planning/Construction Phase

Multi-School (Holston, Burks, Clarke Central, H.T. Edward campus, Gaines) HVAC replacements - Expected completion Fall 2024

Coile Health Center Project - Expected completion October 2024

HTE-Classic City High School Health Center Project - Expected completion October 2024

Cedar Shoals HS - Renovation Project - Expected completion Fall 2025

Clarke MS - Expected completion - Phase 1 - Fall 2024 / Phase 2 - Early 2025

Completed Projects

ELC East - Loaded Dock Repair Project - Completed April 2024

Mutli-School (BHH, CRE, FOW, GNS, HBS, HTE, JJH, JLB, TIM, WDV, WIN) Whiteboard Replacement Project - Completed July 2024

ACCA Bio-Manufacturing Lab (Also includes A/V Lab renovations) - Completed August 2024

Culinary Kitchen @ ACCAcademy - Completed Fall 2023

Clarke Central HS Roof/Masonry Project - Completed Fall 2023

ELC-EAST - Earth Shelter Roof Project - Completion Fall 2023

Cedar Shoals Field House - Completed June 2023

Clarke Central Softball Dugout Expansion - Completed September 2022

Early Learning Center-East @ Old Gaines School - Completed May 2022

Kitchen Upgrade @ HT Edwards Early Learning Center - Completed April 2022

BOE Administrative Offices (595 Prince Ave) - Completed March 2022

Clarke Central Stadium Project - Completed Spring 2021

Cedar Shoals Track Project - Completed Spring 2021

 ACCA Industrial Lab - Completed October 2020

Cedar Shoals Locker Rooms and Old Gym Upgrades - Completed Summer 2020

Clarke Central Softball Concession Stand/Pressbox and Field upgrades - Completed September 2019

Hilsman Middle School - Completed September 2019

Burney-Harris-Lyons Middle School - Completed March 2019

Coile Middle School - Completed March 2019

ACCA Cosmetology Lab - Completed December 2018

Oglethorpe Avenue Elementary - Completed Fall 2018